Updated October 2026

Concrete calculators and cost guides

Concrete is sold by the cubic yard and mixed by the bag, which is why a 12 × 12 ft patio can look like a one-trip job and turn into three. Measure the pour, convert it to cubic yards, and let the calculator tell you whether you need a pallet of bags or a short-load truck.

Smooth exposed concrete slab beside a wall
A slab is priced by volume, not by area. Thickness is the number most people get wrong. Photo: Samuel Zeller (CC0)

Start with the calculator

Cost guides

Quick numbers before you start

Item Typical figure
1 cubic yard27 cubic feet
80 lb bag of mix0.60 cu ft — about 45 bags per yard
60 lb bag of mix0.45 cu ft — about 60 bags per yard
Ready-mix concrete$150–$210 per cubic yard delivered
Bagged concrete$5–$9 per 80 lb bag
Slab thickness, patio or shed4 in
Slab thickness, driveway5 in minimum
Slab installed, plain finish$6–$14 per sq ft
Gravel base4 in compacted
Control joint spacing2–3 ft per inch of slab thickness
Forms and reinforcement set out for a concrete foundation
Footings carry the load; the slab just carries the floor. They are priced differently. Photo: Wikideas1 (CC0)

How concrete quantities work

Concrete is ordered in cubic yards. One yard is 27 cubic feet, which is enough to pour a 4 inch slab about 81 square feet in area. The conversion is always the same: area in square feet × thickness in inches ÷ 12 gives cubic feet, then divide by 27. A 12 × 12 ft patio at 4 inches is 144 × 0.333 = 48 cu ft, or 1.78 cubic yards.

Bagged mix is priced by weight, not by volume, and each bag only yields a fraction of a cubic foot once mixed. That is why a small pour looks cheap per bag and expensive per yard: 1.78 yards is 80 bags of 80 lb mix. Bags stop making sense somewhere around one cubic yard, or roughly 45 bags — above that, a ready-mix short load is cheaper and far less work.

Order 5–10% extra, never the exact calculated volume. Running short mid-pour means a cold joint — a visible seam where one batch set before the next arrived — and cold joints are permanent. Leftover concrete can always become a small pad or be dumped in the forms.

Slab or footing?

A slab is a flat plate poured over a prepared gravel base: patios, shed floors, garage floors, driveways. A footing is a deeper, narrower pour that transfers load into the ground: deck posts, porch columns, foundation walls. Slabs are calculated from area × thickness. Footings are calculated from length × width × depth, and depth has to reach below the local frost line or the ground will heave it apart in winter.

Both use the same calculator. Switch the mode at the top, and remember that the depth figure for a footing is the part buried in the ground — not the part you can see above grade.